MCF-POW-017 Voltage Quality
Claim operationAssurance level AL4Tier CP-3Evidence floor S3Supports CG-05
Objective. Ensure voltage delivered to critical IT and cooling loads stays within equipment tolerance in all source configurations, including on generator and during load swings from AI clusters.
Requirement and evidence
The facility operator shall monitor voltage magnitude, unbalance and short-duration variations at UPS outputs, critical switchboards and a representative sample of rack PDUs, shall compare results with the tolerance of connected equipment (power supply unit specifications and the ITIC/CBEMA or SEMI F47 curves where adopted), and shall investigate excursions.
Evidence required: E2 Configuration and technical state; E3 Operational and observational. Optional: E7. Operating states: NORMAL, EMERGENCY, DEGRADED.
MCF-POW-018 Harmonics
Claim operationAssurance level AL4Tier CP-3Evidence floor S4Supports CG-05
Objective. Ensure harmonic distortion from rectifier-based IT loads, UPS, VFDs and BESS inverters is within limits at the point of common coupling and internally, does not overheat transformers, neutrals or generators, and does not cause resonance with filters or power-factor correction.
Requirement and evidence
The electrical engineer shall perform a harmonic study for the declared load mix covering utility and generator source configurations, and the facility operator shall measure voltage and current harmonics at the PCC and at critical boards. The facility owner shall keep harmonic emissions at the PCC within the limits of the connection agreement (for example IEEE 519 or the applicable IEC 61000-3 limits) and shall derate or specify transformers and generators for measured harmonic content.
Evidence required: E1 Documentary and declarative; E2 Configuration and technical state; E3 Operational and observational. Optional: E7. Operating states: NORMAL, EMERGENCY.
MCF-POW-019 Transient Ride-Through
Claim effectivenessAssurance level AL5Tier CP-5Evidence floor S5Critical to CG-05Supports CG-06
Objective. Demonstrate that critical IT, cooling and control loads ride through grid voltage dips, transfers between sources and switching transients without loss of service, and that the facility meets any fault ride-through obligations of its grid connection.
Requirement and evidence
The electrical engineer shall define the ride-through envelope for each load class (IT, CDU and pump drives, chillers, controls), including source transfers (UPS to bypass, static transfer switch, ATS, generator synchronisation) and grid dips. The facility owner shall verify by commissioning and periodic transfer tests that loads remain online for transfers within the envelope, shall ensure mechanical loads not on UPS restart automatically within the thermal time constant, and shall document compliance with connection-agreement ride-through requirements.
Evidence required: E1 Documentary and declarative; E2 Configuration and technical state; E3 Operational and observational; E4 Validation and test. Optional: E5. Operating states: NORMAL, TRANSITION, EMERGENCY, RECOVERY.
MCF-POW-020 Load-Step Response
Claim effectivenessAssurance level AL5Tier CP-5Evidence floor S5Critical to CG-05Supports CG-03
Objective. Demonstrate that UPS, BESS, generators and the grid connection remain stable under the load steps and synchronous power oscillations produced by large accelerator clusters (collective compute/communication phases, job start and stop, checkpoint pauses and failure-driven drops), and that these dynamics are bounded within the capability of every source.
Requirement and evidence
The facility owner shall characterise the power dynamics of each AI cluster (step magnitude, ramp rate, oscillation amplitude and frequency band), using measured data at sub-second resolution or the accelerator vendor's specified behaviour, and shall verify that UPS rectifier and inverter controls, BESS, generator governors and voltage regulators, and the grid connection tolerate them without instability, protective trips or breach of connection limits. Where they do not, the facility owner shall apply mitigation (accelerator power-smoothing or ramp-limit features, workload scheduling, energy-storage buffering) and shall verify it by test, including a load-step test on generator supply.
Evidence required: E1 Documentary and declarative; E2 Configuration and technical state; E3 Operational and observational; E4 Validation and test. Optional: E5, E7. Operating states: NORMAL, EMERGENCY, TRANSITION.